Town of Matthews issued the following announcement on Apr. 22.
The Town of Matthews continues resurfacing several streets as part of the Town’s resurfacing program.
The Town of Matthews continues resurfacing several streets as part of the Town’s resurfacing program. This project was announced in March. Click here to read the announcement.
Below is an updated schedule for the construction activities. All dates are subject to change.
Residents will have full access to their homes except for short periods of time during this process. Door hangers will be placed on doors of residences a few days prior to work starting. Residents on those streets are asked not to park on those roads while work is underway between 7 a.m. and 5:30 p.m.
Neighborhood or Road | Milling | FDR | Paving |
Matthews Commons | Done | Done | Done |
Windsor Chase | Done | Done | 4/22 |
Streamside | Done | Done | 4/23 |
Brandywine | Done | 4/22-4/23 | 5/11-5/12 |
Kimway | Done | 4/27-4/29 | 5/13 |
Moore Rd. | Done | 4/30 | 5/14 |
Buckton Ln. | Done | 5/1 | 5/14 |
Providence Manor | Done | 5/4-5/6 | 6/1-6/2 |
Chelsea Ct. | Done | 5/7 | 6/3 |
Bubbling Well Rd. | Done | 5/8 | 6/3 |
West McDowell St. | Done | 5/12 | 6/4 |
Team/Crews Rd | Done | 5/13-5/14 | 6/4 |
Crestdale | Done | 5/18-5/19 | 6/8 |
Matthews Plantation | Done | 5/20-5/25 | 6/9-6/10 |
Original source: https://www.matthewsnc.gov/newsview.aspx?nid=6439