TOWN OF MATTHEWS: Updated Schedule for Road Resurfacing Project

Shutterstock 132610877

Town of Matthews issued the following announcement on Apr. 22.

The Town of Matthews continues resurfacing several streets as part of the Town’s resurfacing program.

The Town of Matthews continues resurfacing several streets as part of the Town’s resurfacing program. This project was announced in March. Click here to read the announcement.

Below is an updated schedule for the construction activities.  All dates are subject to change. 

Residents will have full access to their homes except for short periods of time during this process. Door hangers will be placed on doors of residences a few days prior to work starting. Residents on those streets are asked not to park on those roads while work is underway between 7 a.m. and 5:30 p.m.

Neighborhood or Road

Milling

FDR

Paving

Matthews Commons

Done

Done

Done

Windsor Chase

Done

Done

4/22

Streamside

Done

Done

4/23

Brandywine

Done

4/22-4/23

5/11-5/12

Kimway

Done

4/27-4/29

5/13

Moore Rd.

Done

4/30

5/14

Buckton Ln.

Done

5/1

5/14

Providence Manor

Done

5/4-5/6

6/1-6/2

Chelsea Ct.

Done

5/7

6/3

Bubbling Well Rd.

Done

5/8

6/3

West McDowell St.

Done

5/12

6/4

Team/Crews Rd

Done

5/13-5/14

6/4

Crestdale

Done

5/18-5/19

6/8

Matthews Plantation

Done

5/20-5/25

6/9-6/10

Original source: https://www.matthewsnc.gov/newsview.aspx?nid=6439

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS